The interventions include additional berthing capacity, the return of refurbished cranes and the prioritisation of essential cargo as the company works to reduce backlogs at Durban Gateway Terminal
The Port of Durban is facing renewed operational pressure, prompting Transnet to introduce a series of measures aimed at improving cargo movement and reducing vessel backlogs at Durban Gateway Terminal (DGT).
The state-owned logistics company is working with DGT to increase available capacity at the port, with interventions covering vessel berthing, container handling and the movement of cargo from the terminal to inland destinations.
One of the immediate measures involves making Berth 102 available to accommodate geared vessels, which have their own equipment for loading and offloading cargo. The additional berthing capacity will allow some vessels to discharge containers directly, easing pressure on existing terminal operations.
Transnet is also working with DGT to identify vessels that can be diverted to the Ngqura Container Terminal (NCT) in the Eastern Cape. Durban-bound containers discharged at Ngqura will subsequently be transported by smaller geared vessels to Berth 102 and the Point Terminal.
The arrangement is expected to provide shipping lines with an alternative option while the company works to reduce the number of vessels waiting to discharge cargo at Durban.
Equipment availability is another area receiving attention. Transnet Port Terminals (TPT) is bringing ship-to-shore (STS) cranes back into operation at Pier 1 following long-term refurbishment. The final crane is scheduled for commissioning on 20 November and handover to operations on 21 November, bringing all six cranes into operational availability.
Transnet had also assessed whether equipment could be moved from its Cape Town terminals to support operations at DGT. However, the Cape Town Container Terminal and Cape Town Multi-Purpose Terminal are currently unable to release equipment because of increased demand during the deciduous fruit export season.
On the landside, Transnet Freight Rail (TFR) has made additional trains available to move imported containers destined for Gauteng. The company is encouraging cargo owners and logistics operators to use the rail service to speed up the evacuation of containers and reduce pressure on the terminal.
Essential cargo, including pharmaceuticals and automotive components, will also receive priority before vessels berth to support its faster movement through the port.
Transnet acknowledged that the congestion has affected shipping lines, cargo owners and customers across the broader logistics value chain.
The company said reducing the backlog would require sustained implementation of the measures and close coordination between terminal operations, Transnet National Ports Authority, Transnet Freight Rail, shipping lines and customers.
It will continue to provide updates to industry stakeholders as the interventions progress.